When graphs building is finished

hi,

I would like to understand by watching the contents of the graphs directory how it is possible to understand when the graph build is actually completed.

maybe from the stamp.txt file?

what the contents of stamp.txt mean

or … which file is generated last to make sure the graph is working

Hey,

for each profile, the stamp.txt-file is the one generated last. It contains the size of the osm file used to generate the graphs. Its creation should mean that graphs for a particular profile are finished building.

Best regards,
Jakob

1 Like

it is strange that information is entered that you already have … such as the size of the pbf file

perhaps it would be more useful to insert as content the report that is shown at the end of the graph construction logs… graph size… profiles ecc…

Feel free to open an issue with improvement suggestions
or directly conrtibute with a PR

Best regards

1 Like